The direct and indirect costs estimated by a contractor for bidding a project is ₹160000 and ₹20000 respectively. If the mark up applied is 10% of the bid price, the quoted price (in ₹) of the contractor is
- A200000
- B198000
- C196000
- D182000
Construction MaterialsSteel – Composition, material properties and behaviourMCQ1 mark · −1/3 if wrongEasy