A raft foundation of 30 m × 25 m is proposed to be constructed at a depth of 8 m in a sand layer. A 25 m thick saturated clay layer exists 2 m below the base of the raft foundation. Below the clay layer, a dense sand layer exists at the site. A 25 mm thick undisturbed sample was collected from the mid-depth of the clay layer and tested in a laboratory oedometer under double drainage condition. It was found that the soil sample had undergone 50 % consolidation settlement in 10 minutes.
The time (in days) required for 25 % consolidation settlement of the raft foundation will be ____________________. (round off to the nearest integer)
GATE CE 2022 (S1) — Question 55
Soil MechanicsCompaction of soilsNAT2 marksHard
A GATE question every morning
One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.
More on Compaction of soils
- GATE CE 2026 (S2) · Q58A building is proposed in an area having thick deposit of silty clay. The water table is at the ground surface. The saturated unit weight o…
- GATE CE 2025 (S2) · Q32A 6 m thick clay stratum has drainage at both its top and bottom surface due to the presence of sand strata. The time to complete 50% conso…
- GATE CE 2024 (S1) · Q53The total primary consolidation settlement (S c) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. A…
- GATE CE 2023 (S1) · Q41Consider that a force P is acting on the surface of a half-space (Boussinesq’s problem). The expression for the vertical stress ( z) at any…
- GATE CE 2022 (S2) · Q32A concentrically loaded isolated square footing of size 2 m × 2 m carries a concentrated vertical load of 1000 kN. Considering Boussinesq’s…
- GATE CE 2022 (S2) · Q55A saturated compressible clay layer of thickness h is sandwiched between two sand layers, as shown in the figure. Initially, the total vert…