The diagram below shows a river system consisting of 7 segments, marked P, Q, R, S, T, U, and V. It splits the land into 5 zones, marked Z1, Z2, Z3, Z4, and Z5. We need to connect these zones using the least number of bridges. Out of the following options, which one is correct?
Note: The figure shown is representative.


- ABridges on P, Q, and T
- BBridges on P, Q, S, and T
- CBridges on Q, R, T, and V
- DBridges on P, Q, S, U, and V