An Activated Sludge Process (ASP) has an inlet wastewater flowrate of 20000 m/day with a Biochemical Oxygen Demand (BOD) concentration of 250 mg/l. It produces treated wastewater containing 20 mg/l BOD. The aeration tank has a working volume of 6000 m and a biomass concentration of 3000 mg/l. Biological Sludge Residence Time (BSRT) of the system is 6 days. The influent wastewater and the treated effluent from the system have negligible concentrations of biomass. The sludge recycle line from the bottom of the Secondary Sedimentation Tank (SST) to the inlet of the aeration tank has a flowrate of 6000 m/day.
To maintain equilibrium, the flowrate (in m/day) of sludge that is to be wasted from the system is ______ (in integer).
GATE CE 2026 (S1) — Question 63
Water and Waste Water Quality and TreatmentSludge treatment and disposalNAT2 marksMedium
A GATE question every morning
One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.
More on Sludge treatment and disposal
- GATE CE 2026 (S2) · Q27Column I presents common air pollutants, and column II presents treatment technologies commonly employed to control air pollutants. The opt…
- GATE CE 2026 (S2) · Q65In an industry, a cyclone collector with 80 % efficiency is installed for air purification, followed by an electrostatic precipitator with…