A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
- A3
- B9
- C27
- D81
Operations ResearchPERT and CPMMCQ1 mark · −1/3 if wrongEasy