GATE ME 2026 — Question 65

Operations ResearchPERT and CPMNAT2 marksMedium

The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (\(t_o\)), most likely (\(t_m\)), and pessimistic (\(t_p\)) are given in the table below.
Question image
The expected project length is ________ weeks (in integer).