GATE ME 2022 (S2) — Question 41

Production Planning and ControlSchedulingMCQ2 marks · −2/3 if wrongMedium

Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is __________ hours.
Question image
  1. A
    31
  2. B
    33
  3. C
    30
  4. D
    32