Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
Which job(s) has/have critical ratio less than unity?

- AJob N and Job O
- BJob M and Job N
- CJob P
- DJob O and Job P