Consider the following data for a project of 300 days duration. Budgeted Cost of Work Scheduled (BCWS) = Rs. 200 Budgeted Cost of Work Performed (BCWP) = Rs. 150 Actual Cost of Work Performed (ACWP) = Rs. 190 The ‘schedule variance’ for the project is
  1. A
    (−)Rs. 50
  2. B
    (−)50 days
  3. C
    (+)Rs. 50
  4. D
    (+)50 days