GATE CE 2024 (S2) — Question 38

Construction MaterialsConcrete – Constituents, mix design, short-term and long-term propertiesMCQ2 marks · −2/3 if wrongMedium

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q. P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day. Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day. Which one of the following options is CORRECT?
  1. A
    Both P and Q are TRUE
  2. B
    P is TRUE and Q is FALSE
  3. C
    Both P and Q are FALSE
  4. D
    P is FALSE and Q is TRUE
Practise the full 2024-S2 paper
Challenge a friend: WhatsApp Telegram
From RENYXERAThis week's 10-question challengeSame 10 past-GATE questions for everyone this week — see where you stand.
Practise more on Concrete – Constituents, mix design, short-term and long-term propertiesTimed, in the real exam interface · free to start

A GATE question every morning

One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.

Join
Stuck? Ask in the student group