A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000.
Consider the statements P and Q.
P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.
Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.
Which one of the following options is CORRECT?
- ABoth P and Q are TRUE
- BP is TRUE and Q is FALSE
- CBoth P and Q are FALSE
- DP is FALSE and Q is TRUE