GATE CE 2025 (S1) — Question 42

Construction MaterialsConcrete – Constituents, mix design, short-term and long-term propertiesMSQ2 marksEasy

In the context of construction project management, which of the following statements is/are true:
  1. A
    A dummy activity will consume time and resources
  2. B
    The programme evaluation and review technique (PERT) is best suited for projects with large uncertainties in the duration of activities
  3. C
    A Gantt chart is commonly used for identifying the ‘critical path’ of activities in a project
  4. D
    Free float is the amount of time by which the start of an activity can be delayed without causing a delay in the start of a following activity
Practise the full 2025-S1 paper
Challenge a friend: WhatsApp Telegram
From RENYXERAThis week's 10-question challengeSame 10 past-GATE questions for everyone this week — see where you stand.
Practise more on Concrete – Constituents, mix design, short-term and long-term propertiesTimed, in the real exam interface · free to start

A GATE question every morning

One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.

Join
Stuck? Ask in the student group