GATE CE 2021 (S1) — Question 53

Construction MaterialsConcrete – Constituents, mix design, short-term and long-term propertiesNAT2 marksMedium

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
Question image
The total float of the activity “V” (in weeks, in integer) is _____________