Consider the statements P and Q.
P: Client’s Preliminary Estimate is used for budgeting costs toward the end of planning and design phase.
Q: Client’s Detailed Estimate is used for controlling costs during the execution of the project.
Which one of the following options is CORRECT?
- ABoth P and Q are TRUE
- BP is TRUE and Q is FALSE
- CBoth P and Q are FALSE
- DP is FALSE and Q is TRUE

