The project activities are given in the following table along with the duration and dependency.
Which one of the following combinations is correct?

- ATotal duration of the project = 22 days, Critical path is Q → S
- BTotal duration of the project = 20 days, Critical path is Q → T
- CTotal duration of the project = 22 days, Critical path is P → T
- DTotal duration of the project = 20 days, Critical path is P → R